- The draft permit caps NOx at 89.9 tons per year, leaving 11.6 tons of margin before the 100 TPY major source threshold.
- Propane startup and shutdown events emit 4.6 times more NOx per hour than natural gas. If propane use reaches roughly 20% of operations, total NOx crosses the major source trigger.
- MCAQD treats the power plant and future data center as a single regulated source. The data center's diesel generator emissions count against the same cap.
- No data center tenant has been named. No data center emissions have been calculated. The 11.6-ton margin has not been tested against them.
Maricopa County has carried federal nonattainment designations for PM10 particulate matter and ozone for decades.1 The air here already fails to meet health standards. That is the baseline.
Takanock Baccara, LLC has applied to the Maricopa County Air Quality Department (MCAQD) for permission to build and operate 18 natural gas-fired combustion turbines, with propane as a backup fuel, on a 160-acre parcel roughly two miles from thousands of family homes north of Surprise. MCAQD published the draft permit and supporting technical documents for a 30-day public comment period beginning March 4, 2026.2 I read them.
What follows is not a summary of concerns or projections. It is a description of what the permit documents say, calculated against what federal law requires.
The Threshold by Design
Federal law separates air pollution sources into two categories based on how much they emit. Above 100 tons of nitrogen oxides (NOx) per year, a facility is a major source, subject to a different set of requirements: federal Prevention of Significant Deterioration review, mandatory NOx offset purchases in nonattainment areas, and Best Available Control Technology standards at the major source level. Below that number, those requirements do not apply.
The draft permit caps Project Baccara's NOx emissions at 89.9 tons per year.3 The Technical Support Document (TSD) prepared by MCAQD states that Takanock is "taking emission limits 80 to 90% of the major source thresholds."4 Running at 90 percent of the threshold to begin with does not leave a wide margin for error. The question is exactly how wide it is.
The Propane Variable
The permit allows two fuels. On natural gas, each turbine may emit 2.0 parts per million by volume dry (ppmvd) of NOx during normal operation. That is the Best Available Control Technology limit. On propane, that limit rises to 5.0 ppmvd.5 Both figures are in Table 4 of the draft permit.
Propane is authorized specifically for natural gas curtailment events (periods when pipeline supply is reduced due to high regional demand) and periods of high market pricing.6 Natural gas pipelines in Arizona are under maximum load when temperatures push past 110 degrees and every air conditioner in the Valley is running at once. That is when curtailments happen. The permit application assumes propane will account for 10 percent of total annual operating hours.
Emissions during startups and shutdowns are higher than during steady operation, and the difference between fuels is larger during those events. The draft permit sets the NOx rate during natural gas startups and shutdowns at 9.2 pounds per hour per turbine. During propane startups and shutdowns, that figure is 42.2: 33 more pounds per hour per turbine, at the moments when the facility is emitting most.7
Working from the permit's own figures, the annual NOx budget at permitted baseline conditions breaks down as follows:
| Emissions Source | Tons NOx / Year |
|---|---|
| Normal operation, natural gas (2,309 hrs/turbine, 18 turbines) | 60.3 |
| Normal operation, propane (257 hrs/turbine, 18 turbines) | 16.4 |
| Startup and shutdown, natural gas (3,240 events) | 6.5 |
| Startup and shutdown, propane (360 events) | 3.3 |
| Emergency diesel engines (4 units, 50 hrs/yr each) | 2.0 |
| Total at permitted conditions | 88.4 tons |
| Margin to 100 TPY major source trigger | 11.6 tons |
| All figures calculated from Draft Permit P0013417 Tables 2, 3, and 4, and TSD operating parameters. Emission rates are per-turbine permit limits applied to permitted annual operating hours and event counts. | |
That leaves 11.6 tons of margin before the major source trigger. Arizona summers can eat that margin quickly.
Arizona summers create exactly the conditions that push propane use higher. When curtailments happen, propane runs. When market prices spike, propane runs. The permit authorizes both. If propane use reached 20 percent of total operations instead of the assumed 10 percent, a scenario within what Arizona summer conditions can produce, the annual NOx total reaches 100.7 tons. That is 0.7 tons above the major source threshold. The actual breakeven point is 19.4 percent of operations on propane: a shift of fewer than 10 percentage points from the baseline, well within what the permit authorizes and what Arizona summers historically demand.8
A second scenario concerns startup and shutdown events. The permit authorizes a maximum of 3,600 of them per year across all 18 turbines.9 Each time a turbine goes from off to running and back to off, that is one event. The facility does not run all 18 turbines continuously. It spins up what current demand requires and spins down what it does not need. On a volatile summer afternoon with grid demand shifting rapidly, turbines may cycle frequently. The permit does not specify how many of those 3,600 events must occur on natural gas versus propane. If all 3,600 were to occur on propane while normal operating hours remained at the assumed 10 percent propane mix, total facility NOx would reach 111.6 tons. That is arithmetic from the permit tables, not a prediction.
| Scenario | Total NOx (tons/yr) | vs. 100 TPY Trigger |
|---|---|---|
| As permitted (10 percent propane, 360 propane S/S events) | 88.4 | 11.6 below |
| Propane doubles to 20% (summer curtailment scenario) | 100.7 | 0.7 above |
| All 3,600 S/S events on propane, steady-state unchanged | 111.6 | 11.6 above |
| All scenarios calculated from Draft Permit P0013417, Tables 2, 3, and 4. No values have been adjusted or projected beyond the permit's own stated emission rates and maximum operating parameters. | ||
None of this is a prediction that Takanock will operate at these levels. It is a description of what the permit's own numbers produce when you vary the fuel mix within the ranges the permit itself authorizes.
The Single-Source Question
The draft permit covers the power plant. It does not cover the data center, because no tenant has been identified and no data center permit has been filed. The Technical Support Document addresses this directly, in a section titled "Single Source Determination."
MCAQD found that the power plant and the planned data center must be treated as a single regulated source, because the facility's reason for existing is to power a data center. Takanock acknowledged during proceedings before the Arizona Power Plant and Line Siting Committee that Electrical District No. 7 does not have sufficient existing load demand to warrant a 700-megawatt plant absent the data center.4 The TSD states: "MCAQD is treating the power plant and the planned, but not yet applied for, data center as a single source."4
Data centers produce their own NOx emissions, primarily from diesel backup generators required to maintain power during grid outages. A comparable hyperscale facility, Microsoft's 1.3-million-square-foot data center campus in Wisconsin, was permitted for just under 100 tons of NOx per year from 40 backup generators alone.13 The planned Baccara data center is approximately 2 million square feet across two buildings. No tenant has been named, and no permit has been filed for the data center. Its generator fleet and associated emissions have not been calculated. What has been determined, by MCAQD, is that those emissions will count toward the same regulatory accounting as the power plant's 89.9-ton NOx cap, which currently carries 11.6 tons of margin before the major source threshold.
The TSD acknowledges that if the combined power plant and data center emissions exceed major source thresholds, "the power plant could potentially be liable for beginning construction and possibly operation without the required major new source review permit."4 The TSD further states that Takanock "understands and accepts this risk" because it is confident the combined facility will stay below applicable thresholds. That confidence has not been tested against a named tenant or a calculated data center emissions figure.
The data center's emissions have not been calculated, because the tenant has not been named. The calculations above do not include them.
What Crossing the Threshold Would Mean
If a facility operating under a synthetic minor permit (one where the operator voluntarily caps emissions below a major source threshold to avoid the stricter requirements that come with major source classification) exceeds those caps, federal civil penalties under 40 CFR Part 19 can reach $124,426 per day per violation as of January 2025.10 The facility would also face potential retroactive major source review, mandatory purchase of NOx offset credits in the nonattainment market, and possible retrofit requirements to meet major source Best Available Control Technology standards.
These consequences matter. They are also worth placing in context. The penalty structure in federal environmental law was calibrated for a regulatory environment that predates large firms like DigitalBridge, which backs Takanock and manages approximately $16 billion in assets.11 EPA's enforcement policy literature has acknowledged that civil penalties designed to eliminate the economic benefit of noncompliance do not always achieve that goal when the scale of the violating entity and the scale of the investment diverge substantially.12 This is a structural feature of how the law is written, not a claim about intent.
What the Record Shows
The draft permit for Project Baccara was published for public comment in March 2026. The documents are available to anyone who wants to read them. The calculations above use no data that is not in those documents. Every emission rate, every operating hour assumption, every event count comes from tables Takanock submitted and MCAQD published.
What those tables show, when the arithmetic is done, is a facility permitted to run within 11.6 tons of the threshold that would require a different class of regulatory oversight, in a climate where the fuel conditions most likely to push it past that threshold are the conditions that occur every summer.
The Maricopa County Planning and Zoning Commission and the Board of Supervisors retain authority over whether this project proceeds. The permit analysis is in the public record. The question now is a straightforward one: whether the people responsible for that decision have examined it as carefully as the people who will live with the result.